Project Overview

This project involved the fabrication and installation of both temporary and permanent steelwork, fenders and ancillary items for Dolphins 2 & 3 at the Santos Jetty in Port Bonython, SA. Our work included:

  • 3D drafting and drawings for temporary and permanent steelwork
  • Fabrication, blasting and painting of all steelwork
  • Removal of existing fenders, box beam and ancillary steelwork
  • Installation of temporary and permanent steelwork and ancillary Items

For the 2m-below soffit platforms, we designed poly floats to assist with the installation of the steelwork, which proved to be the most cost-effective and safest installation methodology. 

We also had to design a flying fox arrangement to get the steel beams around the raking piles and into their correct position. The project was completed 10 days ahead of the already tight schedule.

Client
Freyssinet Australia
Location
Santos Jetty, Port Bonython, SA